Solar energy

Moholm

Töreboda, Sweden

Phase
Under development
Location
Töreboda
Area
Töreboda
Commissioned
2027
Production
174 GWh

A large and important contribution to the municipality's electricity supply

OX2 AB is developing a large-scale, ground-based solar park in the vicinity of Moholm in Töreboda municipality, Västra Götaland county, in collaboration with concerned landowners. The project covers approximately 175 hectares of land and, when fully developed, will be able to produce approximately 130 GWh of electricity per year from renewable solar energy. Töreboda municipality's total electricity consumption in 2021 was 170 GWh, which means that the completed plant will make a large and important contribution to the energy transition and contribute to the fulfillment of climate goals. 

For more info, please go to Swedish project page

Key facts

Project key facts

Technology
Solar energy
Phase
Under development
Location
Töreboda
Area
Töreboda
Commissioned
2027
Production
174 GWh

What is happening now in the project? 

During 2022 and 2023, preparatory surveys and investigations of the conditions in and around the project area have been carried out. The permit process began in the spring of 2023 through consultation with both authorities and the public. An environmental impact statement has been produced, which was included in the application for a voluntary environmental permit that was submitted to the County Administrative Board in Västra Götaland in 2024. The application is still being processed by the authority. OX2 assesses that a permit decision will come in 2025. 


Continued work 

In parallel with the ongoing permit process, OX2 investigates, together with the network owner in the relevant area, how the planned solar park should be connected to the existing electricity grid. In addition, certain investigations of the conditions in the project area are underway, with the aim of mapping soil conditions, etc. The timetable for establishing the solar park in Moholm is currently unclear, as it depends on the ongoing permit review and grid connection process. OX2 currently assesses that the solar park can be established and ready for operation in 2027 at the earliest.

Do you want to know more?